Schedule
Trade sequencing and project timeline
Noise Compliance Hours
All construction work must comply with condo noise bylaws: Monday–Friday, 9:00 AM – 5:00 PM. No work on weekends or statutory holidays.
Complete
In Progress
Pending
Task / Trade
Wk 1
May 5
May 5
Wk 2
May 12
May 12
Wk 3
May 19
May 19
Wk 4
May 26
May 26
Wk 5
Jun 2
Jun 2
Wk 6
Jun 9
Jun 9
Demolition
Demo Crew
5d
Framing
Carpenter
4d
Electrical Rough-in
Electrician
3d
Plumbing Rough-in
Plumber
3d
Insulation
Insulator
2d
Drywall
Drywall Crew
5d
Painting
Painter
4d
Flooring
Floor Installer
3d
Cabinets
Millwork
3d
Countertops
Stone Fabricator
2d
Backsplash
Tile Setter
2d
Fixtures + Trim
Multi-trade
3d
Punch List
All Trades
2d
Elevator Booking
Condo Board
38d
38 days
Total Duration
May 5
Project Start
Jun 12
Est. Completion