Messages
Communicate with your project team
Mark Fraser
Project Manager
Morning! Quick update — demo crew finished yesterday. Everything went smoothly, no surprises behind the walls.
Mon 9:15 AM
That's great news! Any issues with the plumbing stack?
Mon 9:22 AM
Plumbing stack is in good shape. We did find that the previous owner had done some non-permitted electrical work that we'll need to address. I've added it as a change order — CO-002 for the panel upgrade.
Mon 9:30 AM
Understood. What's the cost impact?
Mon 9:35 AM
$1,200 for the panel upgrade from 100A to 200A. Honestly, it's a good investment — you'd want 200A for the induction cooktop anyway. I've submitted the change order for your approval.
Mon 9:42 AM
Electrical rough-in passed inspection. Moving to insulation next week.
Today 2:15 PM