Budget
Track spending against your approved budget
Original Budget
$95,005
Approved Changes
+$2,000
Actual Spent
$34,500
Remaining
$62,505
Budget vs Actual
Demolition$4,500 / $4,500
Framing$4,000 / $4,000
Electrical$5,800 / $7,600
Plumbing$7,200 / $10,000
Insulation$0 / $1,800
Drywall$0 / $4,200
Painting$0 / $3,500
Flooring$0 / $8,260
Cabinetry$0 / $12,170
Countertops$0 / $4,924
Tile$0 / $1,374
Fixtures & Trim$0 / $8,400
Design$8,500 / $8,500
PM & Insurance$4,500 / $9,140
Contingency (10%)$0 / $8,637
Change Orders
CO-001approved
Additional framing for kitchen island support
+$800
Apr 8, 2025
CO-002approved
Electrical panel upgrade — 100A to 200A
+$1,200
Apr 10, 2025
CO-003pending
Additional blocking for wall-mount TV
+$350
Apr 13, 2025
Payment Milestones
Deposit (20%)
$19,401
PaidDemo Complete (15%)
$14,551
PaidRough-in Complete (25%)
$24,251
Finishes Start (20%)
$19,401
Completion (20%)
$19,401